TBM 2 (also known as TBM B - not exactly inspiring names I
know) recently completed Tunnel 6 and broke through to Muguagou Culvert.
These photos were taken on the traverse across the culvert. One day I'll
get around to writing a bit more bout the project! Oh... I nearly forgot:
TBM means Tunnel Boring Machine. This one has a 4.9m diameter and is made
made by Robbins of the US. The machine achieved an average daily advance
of about 30m.

The business end - the cutter head. Roller cutters are
mounted in the head to grind the rock, which is scooped up in buckets and
transported back by conveyor belt. The spoil is deposited into muck trains
that remove the debris from the tunnel by rail.

The tunnel is lined as excavation advances.
Interlocking hexagonal pre-cast concrete segments are used, giving the the
tunnel the finished lining shown above. The rails are on the back-up
section of the TBM.

The segments are lined up ready for placement as part of the
continuous advance/lining system

The segments are installed using a hydraulic erector.
Here an invert segment is being placed on the traverse of Muguagou
culvert. In tunnel sections, each ring is made up of four segments.
The TBM advances by thrusting off the previously built ring and by gripping the
sides of the tunnel

Two of our intrepid team ensure everything is running
smoothly

The TBM enters the previously constructed culvert section
The Elmers in China Photo Gallery produced by Richard
Elmer. If you have any comments or want to use any photos, drop
me a line! Revised: 16 Jul 2007 09:42:23 +0100.